Complete Streets Grant Sidewalk Project (1 files)

Based on feedback received by the City, Mayor Roxann Wedegarner has made the decision to complete only a portion of the proposed sidewalk network from the Tier 3 Complete Streets Construction Grant received from MassDOT.  The following sections will be completed:

- East side of Chapman Street from Norwood Street to Silver Street;

- North Side of Cleveland Street from Chapman Street to Davis Street;

- South side of Norwood Street from Chapman Street to Lunt Ball Fields.

The following sections will not be completed:

- Birch Street;

- Vernon Street.

Hard copies of the plan set are available for viewing at the City Clerk's Office and at the Greenfield Public Library.

Calendar of Events
Tue, Nov 29, 2022, 5:30 pm
Franklin County Technical School,  82 Industrial Blvd, Turners Falls
Tue, Nov 29, 2022, 6:00 pm - 8:00 pm
via Zoom (link will be posted on the agenda)
Posted to: City Council
Wed, Nov 30, 2022, 4:30 pm
Franklin County Technical School,  82 Industrial Blvd, Turners Falls