The 2019 PAVING SCHEDULE
2019 PAVING SCHEDULE
2019 PAVING SCHEDULE
The following will be the 2019 Paving Schedule:
Wednesday, September 4th:
- Bank Row – RR Underpass to Deerfield Street
- Wisdom Place
- Hope Street – Main Street to Olive Street
- Russell Street – Hope Street to Washington Street
Thursday, September 5th:
- Wells Street – In front of #189
- Pierce Street - Federal Street to Chapman Street
- Beacon Street – High Street to Parkway
Friday, September 6th:
- Conway Street – Main Street to Allen Street
Monday, September 9th:
- Colrain Road – Mohawk Trail to Thayer Road
Wednesday, September 11th:
- Barton Road – Plating of Structures
Monday, September 16th and Tuesday, September 17th:
- Barton Road – Reclamation
Thursday, September 19th:
Friday, September 20th:
- Barton Road – Raise Structures
Monday, September 23rd:
One lane will be open to traffic, however, motorists are requested to seek alternate routes to avoid delays. This schedule is weather dependent.